What a steel framing takeoff should include (and what to ask for)
Updated · 5 min read
Walls
- Studs at the specified spacing, with their gauges
- Top and bottom track, and any deflection or slip track the details call for
- At each opening: headers (built-up or box), header track, king and jack studs, and cripples above and below
- Corners, intersections and jamb packs at concentrated loads
- Bridging and blocking, and strap bracing or shear-wall members where detailed
Floors
- Joists by size and gauge, or proprietary joists such as TradeReady
- Rim track and ledgers
- Beams, and the posts or jamb packs that carry them
- Blocking, web stiffeners and openings for stairs and chases
Roof
- Rafters or roof joists, with lengths measured along the slope
- Ridge, hip and valley members
- Ceiling joists, outriggers and blocking
How it should be organized
By level, then by wall, floor or roof, with each line showing designation, pieces, cut length, linear feet and weight. That lets you check it against the drawings one wall at a time, price it any way you like, and turn it into a supplier order. Lengths should be to the nearest 1/8", the precision steel is ordered in.
Questions that expose a thin takeoff
- Is every member listed by SFIA designation, or just "studs"?
- Which drawings, and which revision, was it taken from?
- What waste allowance is included, and on which materials?
- What's excluded? Fasteners, clips and connectors, sheathing, labor and delivery are common exclusions.
- Does the total weight per square foot look like your other projects?
Every Wheelforge estimate answers these on the page: scope, assumptions and exclusions are listed with the numbers. Read how to price the takeoff, or send us your drawings.